Ebooks, Netflix, and Library Building Projects (Part 63, North Columbus Public Library)


North Columbus Public Library to reopen July 5 after $400,000 renovation. (Columbus Ledger-Enquirer, 6/24/2011)

Excerpt:   The North Columbus Public Library isn’t any bigger but inside it appears that way.

“We’ve really opened it up,” said Christopher Warren, the manager of the South Columbus Public Library.

Warren, who also serves as director of library design for the Chattahoochee Valley Libraries, is overseeing the $400,000 renovation of the branch on Armour Road that began May 1.

“We will be open for business on July 5 just as we said we would,” he said. “We’re on time and under budget."

The funding for the renovation comes from the library system’s reserves. River City Construction is doing the work
.