Still work to do.
Photos by Retiring Guy
Good Neighbor Festival parade
8/8/2017 update, "Will final segment be done in time for Good Neighbor Fest parade?, starts here.
Middleton Good Neighbor Fest takes place August 25-27.
7/15/2017 update, "Finishing touches", starts here.
City of Middleton current construction projects.
7/3/2017 update stars here.
Part 2 features a quick side glance at the new Chocolaterian Cafe, where Scott's Bakery used to conduct business.
6/4/2017 update, "Driving on the newly paved stretch of University Avenue, phase 1 reconstruction", starts here.
Video by Retiring Guy
Audio from
T. C. Boyle’s New Novel Taps the Biosphere’s Erotic Potential. (The New York Times, /11/11/2016)
5/26/2017 update, " University Avenue phase 1 reconstruction: Asphalt paving completed, the videos", starts here.
5/16/2017 update, "University Avenue phase 1 reconstruction: Curb, driveway aprons, and pedestrian islands poured", starts here.
Photos by Retiring Guy
5/6/2017 update, " Phase 1 pavement removal completed" starts here.
Photo and video by Retiring Guy
4/27/2017 update, "Stage 1 traffic shift now in place for reconstruction of University Avenue in Middleton", starts here.
New lane lines and other control devices for Stage 1 traffic shift are now in place.
Original 2/12/2017 post, "Crumbling infrastructure: Reconstruction of University Avenue in Middleton begins next month", starts here.
Photo by Retiring Guy
The green arrow points to the location of the crumbling infrastructure.
Phase 1 is scheduled to be completed in time for the Middleton Good Neighbor Festival parade on August 27, 2017.
Phase 2, from Park to Cayuga, will take place in 2018.
\