Monday, July 22, 2024

Madison Wisconsin street projects update: Sheboygan Avenue and Segoe Road utility replacement and street redesign

 
Segoe Road at Regent Street, looking in the direction of Sheboygan Avenue

Photos by Retiring Guy



Sheboygan/Segoe Redesign



The overall project includes pavement reconstruction, spot replacements of curb and gutter, sidewalk, and driveway aprons. The project also includes improved pedestrian crossings, bike lanes, storm sewer replacement, new storm sewer (existing will remain), partial replacement of sanitary sewer and laterals, partial replacement of water main and services, new street lighting, new pavement markings, and new signs. 

Segoe Road will be reconfigured from 2 lanes in each direction to 1 lane in each direction from Regent Street to Sheboygan Avenue. with the layout shown in Exhibits B and C. This will include median protected bike lanes for safe and comfortable bike access. Additionally, pedestrian crossings will be improved at the intersections of Segoe Road and Sawyer Terrace, Segoe Road and Heather Crest, Segoe Road and Vernon Boulevard, and the north side of Segoe Road & Regent Street. These improvements, which include median refuges and shortened pedestrian crossings, are designed to lower vehicle speeds and improve roadway comfort and safety for pedestrians. [emphasis added]


Other Hilldale/Madison Yard posts:
2024
Hilldale Towers.  (4/17)
What's up next for Madison Yards in Madison WI?  (4/17)

2023

2021
Around the block, Madison WI: Hill Farms apartments.  (10/10/2021)The Hamptons at Hilldale (North Segoe Road and Vernon Boulevard).  (6/21/2021)

2020


2011
Wehrmann's at Hilldale: "I can’t stay in business being someone’s showroom".  (1/28/2011)

No comments:

Post a Comment