Element Collective District, University Research Park development, Madison WI (August 2023 construction site visit)


 
Photos by Retiring G uy






7/20/2023 update starts here

Photos by Retiring Guy






5/2/2023 update starts here

Photos and videos by Retiring Guy










3/19/2023 update starts here

Photos by Retiring Guy




2/3/2023 update starts here

Photos by Retiring Guy






1/2/2023 update starts here

Photos by Retiring Guy






11/7/2022 update starts here

Photos by Retiring Guy






10/15/2022 update starts here

Photos and video by Retiring Guy







9/27/2022 update starts here

Photos and video by Retiring Guy









9/16/2022 update starts here

Photo, close-up and video by Retiring Guy






8/13/2022 update starts here

View of construction site looking northwest
 
Photos by Retiring Guy

View of construction looking east




7/19/2022 starts here

View of construction looking north

Photos and video by Retiring Guy

Closer up


View of site looking east




6/11/2022 update starts here

Photos by Retiring Guy



April 11 update starts here

Photos and video by Retiring Guy






3/13/2022 update starts here 

Photos by Retiring Guy




2/11/2022 update starts here

Photo and videos by Reiting Guy



1/9/2022 update starts here

Photo and video by Retiring Guy


12/19/2021 update starts here




The latest episode of “WisBusiness.com: The Show” spotlights Aaron Olver, managing director at University Research Park in Madison. Olver describes ongoing construction at the corner of Mineral Point Road and Whitney Way, the need for more laboratory space for biotechnology companies, and other trends within one of the nation’s leading research parks.

12/1/2021 update starts here

Photo and video by Retiring Guy


Original 10/29/2021 post starts here

Photos and videos by Retiring Guy


Element District development will be divided into roughly three phases: 
Phase I is the selective clearing and preparation of land for construction, construction of two new public streets, Element Drive and Catalyst Way, the installation of stormwater management facilities, and associated grading; 
Phase II is the construction of the laboratory building, and 
Phase III is the construction of the Element Collective apartments, followed by the food hall, fitness facility, and in a future phase, the hotel. 