Wednesday, September 6, 2017

High Point Road bridge video UPDATE: Finished and ready for your inspection




Videos by Retiring Guy



8/18/2017 update, "Anticipated September 1st completion", starts here.


Photos and videos by Retiring Guy







5/28/2017 update starts here.



5/4/2017 update starts here.








4/24/2017 video update



3/20/2017 update starts here.

Photo and video by Retiring Guy




Work scheduled this week 
  • Continue construction of new median pier cap 
  • Continue excavation of the south abutment area 
  • Continue storm sewer placement 
  • Continue construction of north abutment footings



3/7/2017 update, "Construction of new median pier columns", starts here.



Work scheduled this week.  
  • Complete excavation of the north abutment area 
  • Continue construction of new median pier columns 
  • Continue excavation of the south abutment area 
  • Continue storm sewer placement


2/23/2017 update, "Going....going.....gone", starts here.

The Princeton Club facility is behind me.


High Point Road looking north.

Photos and video by Retiring Guy




Original 2/12/2017 post starts here.

Where I'm standing.  Just before the Beltline curves to the north going past the Point Cinemas.








Photos and video by Retiring Guy

High Point Road bridge over Beltline to be replaced; traffic detoured for 7 months.  (Wisconsin State Journal, 2/2/2017)
The narrow two-lane bridge currently traversing the Beltline isn’t wide enough to accommodate four lanes of traffic, so the existing structure will be taken out and a new one erected. 
The project will also include new bicycle lanes in both directions, and sidewalks on both sides, including a new sidewalk on the west side of the street, from the bridge to the D’onofrio Drive intersection.

High Point Road Bridge Replacement.  (City of Madison Engineering)